Eliwana Rail

QBirt

Scope of work

Construction of 72km of new rail alignment to sub ballast level.

Including:

  • 220 Ha of clearing and grubbing
  • 200,000m3 of topsoils stripping
  • 2M m3 of engineered embankment placement including general fill, transition layer, sub ballast and basecourse
  • 700,000m3 of drill and blast in alignment cuttings
  • Construction of surface drains and levees including 20,000m3 of rock protection
  • Crushing, screening and stabilisation of site won materials to produce compliant fill material
  • Installation of 8km of CSP culverts

Completed Project