Project Scope

QH&M BIRT was engaged for the development of a greenfield satellite mine, supporting the delivery of high-grade ore to the Brockman 4 Mine from 2027 onwards.

Project details

Construction of new min establishment consiting of Haul Roads, Access roads, Pit Roads, Various Mine Facility Pads and Mine Stockpile establishment including:

– 379Ha of clearing
– over 700,000m3 of topsoil strip
– 2.8M m3 of excavation including 400,000m3 of Drill and Blast
– 2.2M m3 of engineering and bulk fill placement
– 300,000m3 of sealed and unsealed basecourse
– 6.5km of CSP Culvert installation
– Other various items inlcuding fencing, Barrier rail, road furntiture and rehabilitation

We do what we say we’ll do, giving our clients confidence from concept through to completion.

Delivery Highlights

Capturing the scale, complexity and quality of delivery at every stage.

Get in touch with our leading civil construction team today

Whether you’re a professional in our field looking to embark on a truly rewarding career, an existing client who wants to get started on a new project or you’re a potential client looking to learn more — get in touch with our team today. We’d love to hear from you.