Ima Ramp Bulk Earthworks

QBirt

Scope of work

Construction of new in pit ramp, roads, removal of mine waste, high grade ore to stockpile, contruction and sealing of access roads into mine and other various earth facilities to sustain current mine capacity.
– 280 Ha of Clearing and Grubbing
– 500k m3 of topsoil and subsoil removal
– 3.7M m3 of multi zoned engineered embankment construction
– 300,000m3 of pavement construction
– Over 2km drainage including RCBCs, CSP culverts and scour protection
– 250,000m2 of 2-coat spray seal and;
– 800,000bcm of drill and blast including grade control.

Completed Project