TAILINGS STORAGE FACILITY (TSF13)

Project Information

Client: South32
Start: January 2018
Project Value: $38,000,000
Location: Groote Eylandt

Description

Construction of new tailings storage facility for the GEMCO manganese mining operations including:

  • 3M m3 o a staged engineered embankment
  • Cut off key trench and seepage collection system
  • Processing, hauling and placing over 50,000 tonnes of specifically graded rock materials
  • Construction of decant ring and;
  • Installation and monitoring of earth settlement plates